Request for Information — a formal written question from the contractor to the architect or engineer seeking clarification on the contract documents.

🏗️

In the Field

RFIs create a paper trail that protects you when the plans are unclear. Log every RFI with date submitted and date answered. Slow RFI responses can be the basis for time extension claims — document the impact of unanswered RFIs in your daily log.

📐

Rule of Thumb

Submit RFIs as early as possible — not when you're standing in front of an ambiguous detail about to pour concrete. A 7-day RFI turnaround time is standard; plan your schedule around that lag.