A written directive from the owner or architect instructing the contractor to perform work immediately, before a formal change order is issued.
🏗️
In the Field
Field orders direct action now; change orders follow with pricing. Never perform field-ordered work without written documentation. Log the field order number in your daily log and price it within the contract-required window.
📐
Rule of Thumb
Price field-ordered work within 7–14 days (check your contract). Late pricing submissions can waive your right to markup.