Service Entrance

The point where the utility's power lines connect to the building's electrical system, including the service conductors, meter, and main disconnect.

πŸ—οΈ

In the Field

Service entrance design is coordinated with the utility company β€” they specify connection type, metering location, and clearances. Underground service requires a conduit sleeve under the foundation. Overhead service requires specific clearances from windows, rooflines, and grade.

πŸ“

Rule of Thumb

Coordinate service entrance location with the utility company at the very start of design β€” changing it later means moving conduit, meters, and panels that are already permitted and installed.