Base Course
The layer of compacted granular material directly below a paved surface, providing strength and load distribution to the pavement above.
🏗️
In the Field
Base course is typically dense-graded aggregate (DGA) or crushed limestone, compacted to 98–100% Proctor. It must be shaped to the finished grade before paving. Any irregularity in the base shows up in the finished pavement.
📐
Rule of Thumb
Base course thickness for parking lots is typically 6 inches; for roads carrying heavy trucks, 8–12 inches or more depending on the pavement design.